云顶国际

Today:
网站地图
友情链接:美狮贵宾会  环亚集团AG  人生就是博官网  凯时K66  人生就是博尊龙凯时  j9九游会  来利国际AG旗舰厅  博天堂918  人生就是博  k8凯发天生赢家  凯发一触即发  AG尊龙凯时  豪运国际  js1996官网  AG九游会  
首页 > English > News Gallery > Company Everts > Company News

Casting Final Template of Cast-in-situ Box Grider of Quanzhou Seacrossing Bridge

Source:    Date:2014-03-19  

On March 14, 2014, the final template of cast-in-situ box girder for Package A1 of Quanzhou Bay Seacrossing Bridge undertaken by the 2nd Engineering Company of MBEC is completed. The proposed box girders are part of right bound of 11th template cast-in-situ girders for approach bridges in South Bank having a length of 116m, design concrete volume of 1623.6 m3 and cast by two times.

The cast-in-situ box girders of 11th template for approach bridge in South Bank for Package A1 is four span continuous prestressing box girders which are composed of left and right bounds having girder depth of 3m, width of 163m and total concrete volume of 4888.8 m3.

In order to guarantee the programme target and drainage safety in rainy season, the MBEC project office has strengthened the leadership, painstakingly organize and manage the construction works, continuously optimize construction proposal, and mobilizes a great deal of human and equipment resources so as to complete the fist construction phase within 23 days starting from mobilization of human and material resources to the first casting laying a solid foundation for subsequent construction works

The Quanzhou Bay Seacrossing Bridge is the key engineering projects in Quanzhou City, starting from Nantang Country in Jingjiang City and ending at Tapu by Spanning Over Quanzhou Bay having a total length of 26.7km, in which marine viaducts have a total length of 12.45km and approach parts on both land have about 14.7km. The bridge type is twin tower separated combined girder cable stay bridge by adopting three column gantry cable tower which is the biggest Seacrossing infrastructure project across bay in Fujian province

up:

next:

云顶国际

网站地图
网站地图